Multiworks were engaged by CPP to construct the substation being utilised for the new wind farm at Bodangora. The site, of which was located within a ravine, contained high-strength rock and required D9 dozers and 35T excavators to shape the new footprint of the substation. Following completion of earthworks, Multiworks worked in with CPP's other electrical contractors to handover the site 5 months later. Some of the other work included within our contract included;

  • Internal Roadways
  • Stormwater drainage and pits
  • Conduits
  • Earthing
Location

Bodangora, NSW

Client

Consolidated Power Projects

Completion

2018

Service

Civil Construction, Construction Project Management

Sector

Water